A new car-free plaza on Thomas Street next to Seattle Center is open, giving Uptown residents and visitors a pedestrian-friendly gateway to the campus.
The Seattle Department of Transportation marked the project's completion with a community celebration on Saturday, Nov. 14, according to SDOT's blog. SDOT Acting Director Angela Brady spoke at the event, which was co-hosted with Seattle Streets Alliance, Uptown Alliance and other local organizations. SDOT said crews recently finished installing new plants and trees.
The finished project includes a car-free space for walking, biking and gathering between 5th Ave N and the alley, a fully protected intersection for cyclists at Dexter Street, a shared-use path on the north side of Thomas Street, and new seating, street trees, landscaping and lighting.
Public benefit funds from a nearby private development paid for the work, according to SDOT.
Years in the making
The project is the latest piece of the Thomas St People Street corridor, a plan to create a pedestrian and bicycle route connecting the Waterfront, Uptown, Seattle Center, South Lake Union and Cascade neighborhoods. The concept dates to a 2013 green street plan. Community advocates pushed for updates in 2019, and a design charrette that year produced three key changes: a half-block closure at 5th and Thomas to create a public plaza next to the Seattle Center skatepark, a 36-foot-wide shared-use path on the north curb, and a protected intersection at Dexter and Thomas, according to the city's project page.
SDOT built the corridor in phases. A Seattle Center-to-Waterfront walking and biking connection was completed in 2021. A second phase covering Thomas Street from 5th Ave N to Dexter Ave N was completed in 2025. The Thomas St Plaza, east of Seattle Center, was installed in 2026.
Earlier in 2026, SDOT also completed the Belltown to Seattle Center Connection Project, filling a gap in the bike network on the southeast edge of Seattle Center near the Space Needle.
Transit links
The corridor supports access to several high-ridership transit lines: the RapidRide E Line on Aurora Ave N, Route 8 along Denny Way and the Seattle Center Monorail connecting to Westlake Station and the regional light rail system.
SDOT said the Thomas Street work is part of its broader People Streets and Public Spaces program, funded through the voter-approved Seattle Transportation Levy.